History of the company

In 2005 the license of the Ministry of architecture and construction of RB for the right of implementation of activity "Design and construction of buildings and constructions of I and II levels of responsibility and to carrying out engineering researches for these purposes" on eleven types has been obtained. In 2008 the license of the Gospromnadzor of the Ministry of Emergency Situations of RB for the right of implementation of activity in the field of industrial safety has been obtained.

For the history our organization with honor has passed a difficult and successful way. Now «SMU №200» - the large and dynamically developing company having reputation of the reliable business partner. The material and technical resources of our enterprise are in continuous development, the new, hi-tech equipment is acquired. The highly skilled collective «SMU №200» is ready to solve any objective with application of the latest technologies.

Effective management of production is our credo!

«SMU №200» with confidence looks in tomorrow. We hope for long-term and effective cooperation!

The list of objects «SMU №200» during 2008 - 2014

  • «1RU. Office of crushing. Replacement of a metalwork. Gallery No. 23»
  • Construction term: 3-4 quarter 2008
  • «1RU. Office of crushing. Replacement of a metalwork. Gallery No. 25»
  • Construction term: The 3rd quarter 2008
  • «1RU.capital repair of a metalwork copra No. 2»
  • Construction term: 3-4 quarter 2008
  • «1RU.capital repair of a metalwork copra No. 4»
  • Construction term: 3-4 quarter 2008
  • «4 RU. Modernization of a fire extinguishing system of mazutonasosny thermal power plant»
  • Construction term: the beginning of works - August, 2008, completion of works - October, 2009
  • «1 RU. Technical re-equipment of SOF-1. Preparation of a depressor, 2nd turn»
  • Construction term: the beginning of works - October, 2008, completion of works - February, 2009
  • «3RU. Reconstruction of office of loading. Knot of loading of granules on the 1st railway way»
  • Construction term: the beginning of works - October, 2008, completion of works - December, 2008
  • «3 RU. Reconstruction of office of drying under a potato storage. 1st turn»
  • Construction term: the beginning of works September of 2008, completion of works - November, 2008
  • «1 RU. Overhaul of construction m / designs of gallery No. 21»
  • Construction term: December, 2008
  • «2RU. Reconstruction of networks of reverse water supply»
  • Construction term: the beginning of works - August, 2009, the end of works - March, 2010
  • «2RU. Technical re-equipment of SOFAS. Trial installation of production of floatation granules by a pelletization method productivity 1000kg/hour»
  • Construction term: the beginning of works - October, 2009, the end of works - July, 2010

  • «4 RU. Installation of automobile scales of BA-60-24-1»
  • Construction term: the beginning of works - August, 2010, completion of works - June, 2011
  • «1 RU. Reconstruction of a mazutokhozyaystvo with installation of the tank volume 5000mz on thermal power plant»
  • Construction term: the beginning of works - May, 2010, completion of works - May, 2012
  • «Knot of coloring of a coarse-crystalline concentrate on 4RU SOFAS»
  • Construction term: the beginning of works - January, 2011, completion of works - November, 2011

  • «2RU. Reconstruction of the scheme of processing of finished goods reagents»
  • Construction term: the beginning of works - November, 2011, the end of works - August, 2012
  • «Thermal power plant of 1RU. Building of the power generating installations with coppers utilizers»
  • Construction term: the beginning of works - September, 2011, 1 stage is handed over in January, 2012, completion of works - April, 2013

  • «1 RU. Reconstruction of reverse water supply of office of granulation»
  • Construction term: the beginning of works - April, 2012, completion of works - June, 2012
  • «1 RU. Technical re-equipment of SOFAS. Modernization of a supply and exhaust ventilation in the building of granulation»
  • Construction term: the beginning of works – March 2012., end of works May of 2016
  • «A platform a water-heating boiler room on thermal power plant 1 RU»
  • Construction term: the beginning of works - June, 2012, completion of works - July, 2012
  • «3 RU. Reconstruction of black oil economy»
  • Construction term: the beginning of works - September, 2012, completion of works - December, 2013
  • «Reconstruction of the operating production. Reconstruction of units with the boiling layer in shop of drying of RU-3 on the basis of GTU»
  • Construction term: 19 months
  • «2RU. Reconstruction of an air-gas path of a water-heating boiler room of boiler shop»
  • Construction term: the beginning of works - July, 2010, completion of works - February, 2012
  • «2RU. Reconstruction of the centralized hot water supply»
  • Construction term: the beginning of works - August, 2010, completion of works - March, 2013
  • «Capital repairs of subcrane ways 2 RU»
  • Construction term: The 2nd quarter 2012
  • «Reconstruction of networks of economic and drinking water supply of 2RU»
  • Construction term: the beginning of works - September, 2012, completion of works - March, 2013
  • «Reconstruction of networks of technical water supply of 2RU»
  • Construction term: the beginning of works - September, 2012, completion of works - February, 2013
  • «Reconstruction of a meat-processing complex of deep processing of meat to 16 tons in live weight in change»
  • Construction term: 19 months
  • «Reconstruction of a material warehouse in Slutsk with expansion of the areas for sugar storage»
  • Construction term: the beginning of works - October, 2013, completion of works - April, 2014
  • «1 RU. Modernization of ventilation in granulation building. Correction»
  • Construction term: from February 01, 2012 to November 27, 2017.
  • «2 RU. Reconstruction of ventilation of the main building Sophie granulation buildings»
  • Construction term: from July 22, 2013 to October 22, 2016
  • «3 RU. Reconstruction of the building №1 granulation with the installation of the granulation plant with a total capacity of 200 t/h on the granulate. First part.»
  • Construction term: from April, 2016 to February, 2018
  • «1 RU. Security measures building №3 freight car fleet in connection with the mine workings III potash mine horizon.
  • Construction term: from April, 2016 to 30 June, 2016